Mobile elevating work platform (MEWP)

Your first-day checklist

Print it and keep it with the machine.

Your manufacturer's manual prevails. This sheet gives the order of the steps; every figure must be read in your own manual, as it changes from one model to the next.

  1. On delivery

    • Walk around it BEFORE you sign
    • Load chart PRESENT and legible
    • Manual, last inspection report and logbook
    • Guardrails, gate and anchor points checked
  2. Unloading

    • Firm level ground, clear of edges
    • Never correct your line on the ramps
    • Platform stowed and low
    • Once loaded: chock and lash to the marked points
  3. BEFORE EVERY shift

    • Full visual inspection + function test
    • Repeat at every change of operator
    • Self-closing gate, guardrails in place
    • Emergency stop: every function dead
    • Locate the GROUND-LEVEL emergency lowering
  4. Before raising

    • Machine level, outriggers firmly down
    • Load-bearing ground: no trench, no cover, no unknown slab
    • Load and occupants within the chart
    • Wind: above the manual’s limit, you do not raise
  5. What kills

    • Power lines — keep the minimum approach distance
    • Tip-over: side slope, an outrigger sinking, overload
    • Crushing against an obstacle overhead
    • Falls: harness where the manual requires one
  6. Statutory inspections

    • Thorough examination on a fixed cycle — six-monthly in France
    • By a competent person, report kept
    • Operator training specific to the type
    • Authorisation to operate comes from the employer

Never do this

  • Never raise without having located the emergency lowering
  • Never travel elevated if the manual forbids it
  • Never come closer to a power line than the minimum distance
  • Never defeat a limit switch, a gate or a tilt alarm
  • Never climb on the guardrails to gain height