Mobile elevating work platform (MEWP)
Your first-day checklist
Print it and keep it with the machine.
On delivery
- Walk around it BEFORE you sign
- Load chart PRESENT and legible
- Manual, last inspection report and logbook
- Guardrails, gate and anchor points checked
Unloading
- Firm level ground, clear of edges
- Never correct your line on the ramps
- Platform stowed and low
- Once loaded: chock and lash to the marked points
BEFORE EVERY shift
- Full visual inspection + function test
- Repeat at every change of operator
- Self-closing gate, guardrails in place
- Emergency stop: every function dead
- Locate the GROUND-LEVEL emergency lowering
Before raising
- Machine level, outriggers firmly down
- Load-bearing ground: no trench, no cover, no unknown slab
- Load and occupants within the chart
- Wind: above the manual’s limit, you do not raise
What kills
- Power lines — keep the minimum approach distance
- Tip-over: side slope, an outrigger sinking, overload
- Crushing against an obstacle overhead
- Falls: harness where the manual requires one
Statutory inspections
- Thorough examination on a fixed cycle — six-monthly in France
- By a competent person, report kept
- Operator training specific to the type
- Authorisation to operate comes from the employer
Never do this
- Never raise without having located the emergency lowering
- Never travel elevated if the manual forbids it
- Never come closer to a power line than the minimum distance
- Never defeat a limit switch, a gate or a tilt alarm
- Never climb on the guardrails to gain height